energy.wikisort.org - Power_plant

Search / Calendar

The Alvin W. Vogtle Electric Generating Plant, also known as Plant Vogtle (/ˈvɡəl/),[5] is a two-unit nuclear power plant located in Burke County, near Waynesboro, Georgia, in the southeastern United States. It is named after a former Alabama Power and Southern Company board chairman, Alvin Vogtle.

Plant Vogtle
Vogtle 1 & 2 containment buildings and cooling towers
Official nameAlvin W. Vogtle Electric Generating Plant
CountryUnited States
LocationBurke County, Georgia
Coordinates33°8′36″N 81°45′38″W
StatusOperational
Construction beganUnit 1–2: August 1, 1976
Unit 3: June 22, 2009
Unit 4: June 22, 2009
Commission dateUnit 1: June 1, 1987
Unit 2: May 20, 1989
Unit 3: Second Quarter 2023 (planned)
Unit 4: Fourth Quarter 2023 (planned)
Construction costUnits 1–2: $8.87 billion (1989 USD)[1]
($16.4 billion in 2020 dollars[2]) Units 3–4: $30 billion (estimated)[3]
Owner(s)Georgia Power (45.7%)
OPC (30%)
MEAG (22.7%)
Dalton Utilities (1.6%)
Operator(s)Southern Nuclear
Nuclear power station
Reactor typePWR
Reactor supplierWestinghouse
Cooling towers2 × Natural Draft
(for Units 1–2)
2 × Natural Draft
(under construction)
Cooling sourceSavannah River
Thermal capacity2 × 3626 MWth
Power generation
Units operational1 × 1150 MW
1 × 1152 MW
Make and model2 × WH 4-loop (DRYAMB)
Units cancelled2 × 1113 MW
Units under const.2 × 1117 MW AP1000
Nameplate capacity2302 MW
Capacity factor95.09% (2017)
91.25% (lifetime)
Annual net output19,176 GWh (2017)
External links
WebsitePlant Vogtle
CommonsRelated media on Commons

[4]

Each unit has a Westinghouse pressurized water reactor (PWR), with a General Electric steam turbine and electric generator. Units 1 and 2 were completed in 1987 and 1989, respectively. Each unit has a gross electricity generation capacity of 1,215 MW, for a combined capacity of 2,430 MW.[6] The twin natural-draft cooling towers are 548 ft (167 m) tall and provide cooling to the plant's main condensers. Four smaller mechanical draft cooling towers provide nuclear service cooling water (NSCW) to safety and auxiliary non-safety components, as well as remove the decay heat from the reactor when the plant is offline. One natural-draft tower and two NSCW towers serve each unit. In 2009, the Nuclear Regulatory Commission (NRC) renewed the licenses for both units for an additional 20 years[7] to 1/16/2047 for Unit 1,[8] and 2/9/2049 for Unit 2.[9][10] During the construction of Vogtle's first two units, capital investment required jumped from an estimated $660 million to $8.87 billion.[1] ($16.4 billion in 2020 dollars[2])

Two additional units utilizing Westinghouse AP1000 reactors are under construction.[11] Natural-draft type cooling towers were also selected, and the two new cooling towers are nearly 600 ft (180 m) tall. The units have suffered several delays and cost overruns. The certified construction & capital costs for these two new units were originally $14 billion, according to the Seventeenth Semi-annual Vogtle Construction Monitoring Report in 2017.[12] This last report blames the latest increase of costs on the contractor not completing work as scheduled. Another complicating factor in the construction process is the bankruptcy of Westinghouse in 2017.[13] In 2018 costs were estimated to be about $25 billion.[3] By 2021 they were estimated to be over $28.5 billion.[14] Upon completion of Units 3 and 4 in 2023, Vogtle will become the largest nuclear power station in the United States.


Reactor data


The Vogtle Electric Generating Plant has two operational reactors with two additional units under construction.

Reactor unit Reactor type Capacity (MWe) Construction
started
Grid
connection
Commercial
operation
Shutdown
Net (Summer) Gross
Vogtle-1[15] Westinghouse
4-loop
1150 1229 August 1, 1976 March 27, 1987 June 1, 1987
Vogtle-2[16] 1152 April 10, 1989 May 20, 1989
Vogtle-3[17] AP1000 1117 1250 June 22, 2009[18] End of the first quarter of 2023
(Projected)[19]
Vogtle-4 Fourth quarter of 2023
(Projected)[19]

Power uprate


In 2008, both reactors were increased in power by 1.7% by an "Appendix K" uprate,[20] also called a Measurement Uncertainty Recapture (MUR) uprate. Measurement uncertainty recapture power uprates are less than 2 percent, and are achieved by implementing enhanced techniques for calculating reactor power. This involves the use of state-of-the-art feedwater flow measurement devices to more precisely measure feedwater flow, which is used to calculate reactor power. More precise measurements reduce the degree of uncertainty in the power level, which is used by analysts to predict the ability of the reactor to be safely shut down under postulated accident conditions.[21] Because the reactor power can now be calculated with much greater accuracy than with the old venturi type measurement, the plant can safely run within a tighter margin of error to its limits. The new flowmeter works by comparing the time it takes ultrasonic sound pulses to travel upstream versus downstream inside the pipe, and uses the time differential to figure the flow rate of the water in the pipe.

The NRC approved Vogtle's License Amendment Request (LAR) in March 2008. The NRC staff determined that Southern Nuclear could safely increase the reactor's power output primarily through more accurate means of measuring feedwater flow. NRC staff also reviewed Southern Nuclear's evaluations showing that the plant's design can handle the increased power level.[22] Unit 1 was uprated during its Spring 2008 refueling outage, and Unit 2 was uprated in the Fall outage of the same year.


Incidents and accidents



Loss of power


A loss of electrical power in the plant occurred on March 20, 1990.

At 9:20 a.m., a truck carrying fuel and lubricants in the plant's 230 kV switchyard backed into a support column for the feeder line supplying power to the Unit 1-A reserve auxiliary transformer (RAT). At the time, the 1-B RAT was de-energized for maintenance and RAT 1-A was powering both trains of emergency electrical power. The non-emergency electrical trains were being powered by back-feeding from the switchyard through the main step-up transformer to the 1-A and 1-B unit auxiliary transformers (UAT). Additionally, emergency diesel generator (EDG) 1-B was out of service for planned maintenance. After the power loss, EDG 1-A failed to start due to a protective safety trip. The resulting loss of electrical power in the plant's "vital circuits" shut down the residual heat removal (RHR) pump that was cooling the core of Unit 1 (which was nearing the end of a refueling outage) and prevented the backup RHR from activating. Even though Unit 1 was offline at the time, residual heat from the natural decay of the radioactive fuel must be removed to prevent a dangerous rise in core temperature. While the non-safety power was not interrupted, there was no physical connection between the vital and non-vital electrical trains, preventing the vital trains from receiving power from the unaffected path through the UATs.

At 9:40 a.m., the plant operators declared a site area emergency (SAE) per existing procedures which called for an SAE whenever "vital" power is lost for more than 15 minutes. At 9:56 a.m., after trying multiple times to start the 1-A EDG normally, plant operators performed an emergency startup of the EDG by activating the generator's emergency start "break-glass" which bypassed most of the EDG's safeties and forced it to start. The startup was successful. RHR-A was then started using power from EDG-A. With core cooling restored, the SAE was downgraded to an alert at 10:15 a.m. At 11:40 a.m., crews energized RAT 1-B which had been shut down for maintenance, restoring power to the "B" safety electrical train. At 12:57 p.m., the "A" safety train was switched from the EDG to RAT 1-B and the EDG was shut down. With both trains receiving offsite power, the alert was terminated at 1:47 p.m.

The temperature of the Unit 1 core coolant increased from 90 °F (32 °C) to 136 °F (58 °C) during the 36 minutes required to re-energize the A-side bus. Throughout the event, non-vital power was continuously available to Unit 1 from off-site sources. However, the Vogtle electrical system was not designed to permit easy interconnection of the Unit 1 vital busses to non-vital power or the Unit 2 electrical busses.[23] Since this incident, Plant Vogtle has implemented changes to the plant that allow the non-vital electrical buses to transfer power to the vital buses in this type of scenario.

This electrical fault also affected Unit 2 by causing breakers in the 230 kV switchyard to trip, cutting off power to RAT 2-B and vital bus "B." EDG 2-B subsequently started and restored power to the vital bus. At the same time, the electrical disturbance from the falling line striking the ground was detected by protective safeties on the Unit 2 main step-up transformer and a protective relay actuated, opening the transformer's output breaker. This caused a full load rejection to Unit 2, leading to a turbine trip and subsequently, a reactor scram. After Unit 2 tripped, the "B" non-vital electrical train lost power as it attempted to transfer from UAT 2-B (powered by the turbine generator) to the failed RAT 2-B, causing two of the reactor coolant pumps and one of the main feedwater pumps to trip. Despite this, plant cool-down proceeded safely. At 9:03 p.m., the RAT 2-B breakers in the switchyard were reset and offsite power was restored to the vital and non-vital "B" electrical trains, allowing reactor coolant pumps 2 and 4 to be restarted. EDG 2-B was shutdown. It was later determined that the fault disturbance caused by the line falling was not of significant magnitude to trip the protective relay per design and should not have caused Unit 2 to shut down. Further investigation found that current transformers on the main transformer were improperly set. The controls were adjusted to the proper setting. Had the CTs been properly set initially, the Unit 2 would have remained online.


Units 3 and 4



Planning phase


Construction underway at Vogtle, October 2011
Construction underway at Vogtle, October 2011
Vogtle Unit 3 Condenser B time-lapse video

On August 15, 2006, Southern Nuclear formally applied for an Early Site Permit (ESP) for two additional units. The ESP determined whether the site was appropriate for additional reactors, and this process is separate from the Combined Construction and Operating License (COL) application process.[24] On March 31, 2008, Southern Nuclear announced that it had submitted an application for a COL, a process which would take at least 3 to 4 years.[25] On April 9, 2008, Georgia Power Company reached a contract agreement for two AP1000 reactors designed by Westinghouse; owned by Toshiba. Westinghouse partnered with the Shaw Group (Baton Rouge, LA) and its Stone & Webster division to manage the project with Westinghouse responsible for engineering, design, and overall management, and Shaw responsible for manufacturing the pre-fabricated component modules and managing the on-site construction.[26] The contract represented the first agreement for new nuclear development in the United States since the Three Mile Island accident in 1979, and it received approval from the Georgia Public Service Commission on March 17, 2009.[26][27]


Construction


On August 26, 2009, the Nuclear Regulatory Commission (NRC) issued an Early Site Permit and a Limited Work Authorization. Limited construction at the new reactor sites began, with Unit 3 then expected to be operational in 2016, followed by Unit 4 in 2017, pending final issuance of the Combined Construction and Operating License by the NRC.[28][29]

In December of 2011, a 19th revision was written for the AP1000 Design Certification, which effectively included a complete redesign of the containment building:

The wall is appropriately reinforced and sized where the composite wall module joins the reinforced concrete sections and as appropriate to accommodate seismic loads and aircraft loads. This design is new to the amendment; previously the structure was all reinforced concrete. [emphasis added]

As this change to the design requirements was made after engineering contacts were already signed and manufacturing had begun on the reactor's long-lead-time components, it resulted in a halting of construction as the containment building had to be re-designed.[30]

The operational dates have since slipped to 2022 and 2023 for Units 3 and 4, respectively.

On February 16, 2010, President Barack Obama announced $8.33 billion in federal loan guarantees toward the construction cost,[31] although as of December 2013, Georgia Power had not availed itself of those guarantees, at first awaiting the construction license, and after the construction stop lawsuit outcome. The expected building cost for the two reactors was $14 billion.[32] Georgia power's share was around $6.1 billion, while remaining ownership of the two reactors is split among Oglethorpe Power Corp., the Municipal Electric Authority of Georgia (MEAG Power), and Dalton Utilities.[33]

In February 2012, the NRC approved the construction license of the two proposed AP1000 reactors at Vogtle.[34] NRC Chairman Gregory Jaczko cast the lone dissenting vote on plans to build and operate the two new nuclear power reactors, citing safety concerns stemming from Japan's 2011 Fukushima nuclear disaster, saying, "I cannot support issuing this license as if Fukushima never happened."[35] One week after Southern Company received the license to begin construction, many environmental and anti-nuclear groups sued to stop the expansion project, claiming "public safety and environmental problems since Japan's Fukushima-Daiichi nuclear reactor accident have not been taken into account".[36] On July 11, 2012, the lawsuit was rejected by the Washington D.C. Circuit Court of Appeals.[37]

In February 2013, the project's construction contractor, Shaw, was purchased by Chicago Bridge & Iron Company (CB&I). On March 12, 2013, construction on Unit 3 officially began with the pour of the basemat concrete for the nuclear island.[38] This operation was completed on March 14.[39] During the weekend of June 1, 2013, assembly of the containment vessel began with the bottom head of the vessel being lifted into place on the nuclear island.[40] By June 2013, the construction schedule had been extended by at least 14 months.[41] On November 21, 2013, the basemat pour for Unit 4 was completed.[42]

In February 2014, the Department of Energy approved a $6.5 billion loan guarantee for Southern Company subsidiary Georgia Power and Oglethorpe Power Corp. The Department of Energy initially demanded a credit subsidy fee, but the demand was ultimately dropped given the financial strength of Southern Co. and the Vogtle project.[43][44][45]

Further delays and cost increases were incorporated in a revised schedule in early 2015. As a result of the increased delays and cost overruns, contractor CB&I exited the project and Westinghouse took direct control of the project as contractor and hired construction firm Fluor to replace CB&I/Shaw on-site managing the day-to-day work. Westinghouse purchased certain assets of the former Shaw Group from CB&I to allow the project to go forward. In 2016, Southern Company and Westinghouse added construction firm Bechtel to the project to share construction management responsibilities.[46]

Recent construction milestones include setting the final of the "big six" structural modules for Unit 3 (CA-02 and CA-03, which form the walls of a storage tank that is part of the reactor's passive cooling system). The "big six" modules also include the previously installed CA-01, CA-04, and CA-05 in-containment structural modules, as well as the previously installed CA-20 structural module which forms part of the internal structure of the auxiliary building, containing many of the reactor's support systems. CA-02 and CA-03 were placed within the containment vessel in May 2016. The setting of these modules is a fairly significant milestone and allows other construction activities to commence. In June 2016, the final reactor coolant pump for Unit 3 was received on site. In November 2016, the reactor vessel for Unit 3 was set within the nuclear island. 2017 progress includes the installation of the reactor coolant loop piping and both steam generators at Unit 3. Progress has also been made in the turbine, auxiliary, and annex building. Unit 4 has also seen progress with the installation of the final two "big six" structural modules. Construction of both cooling towers is complete, with each nearly 600 ft (180 m) tall.[citation needed]


Westinghouse bankruptcy 2017

In March 2017, Westinghouse Electric Company filed for Chapter 11 bankruptcy due to losses from its two U.S. nuclear construction projects.[47] The U.S. government has given $8.3 billion of loan guarantees to help finance construction of the Vogtle reactors,[48] and a way forward to completing the plant has been agreed upon.[49] On July 31, 2017 Southern Company division, Southern Nuclear, officially took over construction from Westinghouse and opened a bid for a new construction management contract to manage the day-to-day work on the site. Southern received bids from both Fluor and Bechtel. On August 31, 2017, Southern announced its decision to move forward with Bechtel to be the day-to-day construction manager for the remainder of the project. Bechtel will replace Fluor, who will no longer be involved in the project.[50]


Continuation of construction approved 2017


In November 2017 the Georgia Public Service Commission (GPSC) requested additional documentation following concerns that design blueprints had not been approved by appropriately licensed engineers, which has legal implications. On December 21, 2017, the PSC approved the continuation of construction on Units 3 and 4, with conditions that reduced the costs that can be recovered from ratepayers over the life of the project,[51] causing a scheduled monthly consumer rate increase of $3.78 after first power.[19]

In the February 2018 Vogtle Construction Monitoring Report (VCM), GPSC approved November 2021 and November 2022 as the target in-service dates for Units 3 & 4 respectively. The report notes that the project is being completed on an accelerated schedule and is currently tracking ahead of the 2021 & 2022 in-service target dates.[52]

In August 2018 a $2.3 billion increase in costs was recognized.[53] The total cost, including financing costs, is estimated at about $25 billion.[3] In September 2018, in order to sustain the project, Georgia Power agreed to pay an additional proportion of the costs of the smaller project partners if the cost of completion went beyond $9.2 billion.[54]

In March 2019 further federal loan guarantees of $3.7 billion were given to the various build partners, taking total federal loan guarantees up to $12 billion. The Georgia Power CEO said the loan guarantees played a key role in reducing financing costs for the build.[55] Also in March 2019, Georgia Power confirmed that the Unit 3 containment cap had been lowered into place and the reactor would be ready to load nuclear fuel in 2020.[56] This was preceded by the containment vessel third ring, as well as reactor coolant pump and polar crane installation in unit 3 during 2018 and 2019. The containment vessel top head was set during a site visit by Secretary of Energy Rick Perry and executives of the plant's owners. Recent progress on unit 4 includes the installation of the final steam generator and pressurizer. Unit 4 is being constructed utilizing lessons learned from Unit 3 and from the failed Virgil C. Summer Nuclear Generating Station (V.C. Summer) project and as a result the order in which some components are being installed has been modified.[citation needed] On November 22, 2019 the third ring of the containment vessel was set for unit 4, and on December 8, 2019 the unit 3 shield building roof was set above the unit 3 containment vessel. On December 16, 2019 the control room of unit 3 became operational and is now available for testing systems. On February 11, 2020, Southern Nuclear announced that the final concrete placement inside the Unit 3 containment vessel was completed which will allow installation of the reactor's fueling machine. As of February 2020, assembly continues on the final top most vertical feature of the overall Unit 3 reactor building, the passive containment cooling system storage tank, which will be set on top of the Shield Building Roof.

A three month delay to completion of both units was announced in October 2021, with unit 3 expected operational in the third quarter of 2022 and unit 4 in the second quarter of 2023.[57] In August 2022 a further delay was announced, first quarter of 2023 for unit 3 and the fourth quarter of 2023 for unit 4. Costs were expected to rise to over $30 billion due to the delays.[58]


Fuel Load Start


On October 14, 2022, Vogtle Unit 3 had begun nuclear fuel load, to be followed by startup testing.[59]


Surrounding population


The Nuclear Regulatory Commission defines two emergency planning zones around nuclear power plants: a plume exposure pathway zone with a radius of 10 miles (16 km), concerned primarily with exposure to, and inhalation of, airborne radioactive contamination, and an ingestion pathway zone of about 50 miles (80 km), concerned primarily with ingestion of food and liquid contaminated by radioactivity.[60]

The 2010 U.S. population within 10 miles (16 km) of Vogtle was 5,845, a decrease of 16.3 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within 50 miles (80 km) was 726,640, an increase of 8.8 percent since 2000. Cities within 50 miles (80 km) include Augusta, GA (26 miles (42 km) to city center).[61]


Seismic risk


The Nuclear Regulatory Commission's estimate of the risk each year of an earthquake intense enough to cause core damage to either reactor at Vogtle was 1 in 140,845, according to an NRC study published in August 2010.[62][63]


See also



References


  1. Moens, John (March 18, 2005). "U.S. Nuclear Plants - Vogtle". Energy Information Administration, U.S. Department of Energy. Archived from the original on July 26, 2018. Retrieved March 2, 2007.
  2. Johnston, Louis; Williamson, Samuel H. (2022). "What Was the U.S. GDP Then?". MeasuringWorth. Retrieved February 12, 2022. United States Gross Domestic Product deflator figures follow the Measuring Worth series.
  3. Walton, Rod (9 August 2018). "Vogtle Cost Upgrade Causes Rethinking of $25B Nuclear Plant's Future". Power Engineering. Retrieved 16 August 2018.
  4. Press, Associated. "Georgia nuclear plant's cost now forecast to top $30 billion". Georgia Public Broadcasting. Retrieved 2022-10-29.
  5. "Inside the Nuclear Energy Renaissance: Plant Vogtle". Southern Company. 7 Jan 2014. Archived from the original on 2021-12-13. Retrieved 26 May 2017.
  6. "Plant Vogtle - Southern Company". Southern Company. Archived from the original on 2007-02-05. Retrieved 2007-03-02.
  7. Pavey, Rob (June 4, 2009). "Licenses for Vogtle current reactors renewed". Augusta Chronicle. Retrieved 2009-06-05.
  8. "Vogtle Electric Generating Plant, Unit 1". NRC. Nuclear Regulatory Commission. 2017-02-10. Retrieved 18 March 2018.
  9. "Vogtle Electric Generating Plant, Unit 1". NRC. Nuclear Regulatory Commission. 2017-02-10. Retrieved 18 March 2018.
  10. Gertner, Jon (July 16, 2006). "Atomic Balm?". The New York Times.
  11. Pavey, Rob (November 22, 2009). "Vogtle lays groundwork for first U.S. reactors in decades". Augusta Chronicle. Retrieved 2009-10-22.
  12. "Seventeenth Semi-Annual Construction Monitoring Report for Plant Vogtle Units 3 and 4". Georgia Power. August 2017.
  13. Yamazaki, Makiko; Kelly, Tim (29 March 2017). "Toshiba's Westinghouse files for bankruptcy as charges jump". reuters.com. Retrieved 29 March 2017.
  14. "'Outrageous' price tag: Plant Vogtle cost doubles to $28.5 billion as other owners balk".
  15. "Vogtle-1". PRIS. IAEA. 2018-03-18. Retrieved 18 March 2018.
  16. "Vogtle-2". PRIS. IAEA. 2018-03-18. Retrieved 18 March 2018.
  17. "Vogtle-3". PRIS. IAEA. 2013-11-21. Retrieved 22 November 2013.
  18. "Document Filing #123793". psc.ga.gov. 2009-10-23. Retrieved 2022-10-27.
  19. "Further delay in startup of Vogtle AP1000s". WNN. 2022-02-18. Retrieved 2022-06-01.
  20. "NRC: 10 CFR Appendix K to Part 50—ECCS Evaluation Models". www.nrc.gov.
  21. "NRC: Power Uprates". www.nrc.gov.
  22. "NRC: News Release - 2008-043 - NRC Approves Power Uprate for Vogtle Nuclear Power Plant". 12 May 2009. Archived from the original on 12 May 2009.
  23. "NRC: Information Notice No. 90-25: Loss of Vital AC Power With Subsequent Reactor Coolant System Heat-Up". www.nrc.gov.
  24. "NRC: Early Site Permits - Licensing Reviews". United States Nuclear Regulatory Commission. Retrieved 2007-05-31.
  25. O'Grady, Eileen (March 31, 2008). "Southern utilities apply for new nuclear licenses". Reuters. Retrieved 2008-04-02.
  26. MacAlister, Terry (April 9, 2008). "Westinghouse wins first US nuclear deal in 30 years". London: Guardian News and Media Limited. Retrieved 2008-04-09.
  27. "Two Nuclear Reactors Get Green Light". The Atlanta Journal-Constitution. Archived from the original on July 26, 2018. Retrieved April 18, 2009.
  28. "Southern Company Plant Vogtle Media Guide" (PDF) (Press release). Southern Company. June 2011. Archived from the original (PDF) on 2011-12-27. Retrieved November 1, 2011.
  29. "Vogtle Units Receive NRC Staff Approval for Final Safety Report" (Press release). Southern Company. August 9, 2011. Archived from the original on July 26, 2018. Retrieved November 20, 2011.
  30. "Root cause of Vogtle and VC Summer delays". www.ans.org. Retrieved 2022-04-07.
  31. "Obama Administration Announces Loan Guarantees to Construct New Nuclear Power Reactors in Georgia". The White House Office of the Press Secretary. Archived from the original on 21 January 2017. Retrieved 2010-04-30.
  32. Rob Pavey (May 11, 2012). "Price of Vogtle expansion could increase $900 million". The Augusta Chronicle. Retrieved July 25, 2012.
  33. Henry J. Pulizzi; Christine Buurma (Feb 16, 2010). "Obama Unveils Loan Guarantees for Nuclear Plant". wsj. Retrieved 27 April 2014.
  34. Abernethy, C. (February 9, 2012). "NRC Approves Vogtle Reactor Construction". Nuclear Street. Retrieved February 9, 2012.
  35. Ayesha Rascoe (Feb 9, 2012). "U.S. approves first new nuclear plant in a generation". Reuters.
  36. Kristi E. Swartz (February 16, 2012). "Groups sue to stop Vogtle expansion project". The Atlanta Journal-Constitution.
  37. Rob Pavey (July 12, 2012). "Court rejects legal challenge to Plant Vogtle construction license". The Augusta Chronicle.
  38. The Augusta Chronicle (March 13, 2013). "Concrete poured for new Vogtle reactor foundation". The Augusta Chronicle. Retrieved March 14, 2013.
  39. Mark Williams (March 14, 2013). "First nuclear concrete placed at Plant Vogtle expansion". Georgia Power. Archived from the original on July 26, 2018. Retrieved March 14, 2013.
  40. Pavey, R. (June 3, 2013). "Vogtle's heaviest component to date moved into place". The Augusta Chronicle. Retrieved June 3, 2013.
  41. Matthew L. Wald (June 11, 2013). "Atomic Power's Green Light or Red Flag". The New York Times. Retrieved July 12, 2013.
  42. "Construction underway of second Vogtle AP1000". World Nuclear News. World Nuclear Association. November 22, 2013. Retrieved November 22, 2013.
  43. "Southern Company subsidiary, DOE finalize Vogtle nuclear project loan guarantees".
  44. "DOE finalizes $6.5bn loan guarantee for new Plant Vogtle nuclear reactors". www.power-eng.com.
  45. Wald, Matthew L. (18 February 2014). "Loan Program for Reactors Is Fizzling" via NYTimes.com.
  46. "Plant Vogtle on track after schedule revised".
  47. DiNapoli, Jessica; Yamazaki, Makiko (9 March 2017). "Toshiba's Westinghouse brings in bankruptcy lawyers; disclosure deadlines loom". www.reuters.com. Reuters. Archived from the original on 13 December 2018. Retrieved 21 February 2019.
  48. "Loan Programs Project Under Construction: Vogtle". Retrieved 7 September 2017.
  49. Tom Hals, Makiko Yamazaki, Tim Kelly (30 March 2017). "Huge nuclear cost overruns push Toshiba's Westinghouse into bankruptcy". Reuters. Retrieved 31 March 2017.{{cite news}}: CS1 maint: multiple names: authors list (link)
  50. "Bechtel Selected to Complete Construction of US Nuclear Plant Expansion".
  51. Corwin, Tom (December 21, 2017). "Plant Vogtle growth wins approval, penalties from Public Service Commission". Savannah Morning News. Retrieved December 21, 2017.
  52. "Eighteenth Semi-annual Vogtle Construction Monitoring Report" (PDF). www.georgiapower.com. February 2018. Retrieved 3 April 2018.
  53. "Progress at Vogtle, but cost forecast rises". World Nuclear News. 9 August 2018. Retrieved 16 August 2018.
  54. "Vogtle owners vote to continue construction". World Nuclear News. 27 September 2018. Retrieved 28 September 2018.
  55. "Perry: Vogtle project is 'critically important'". World Nuclear News. 22 March 2019. Retrieved 22 March 2019.
  56. Bynum, Russ (2019-03-22). "Trump adds $3.7B in support to finish 2 new nuclear reactors". AP NEWS. Retrieved 2019-03-25.
  57. "More delays for Vogtle 3&4". Nuclear Engineering International. 26 October 2021. Retrieved 26 October 2021.
  58. "Vogtle NPP faces more possible delays". Nuclear Engineering International. 3 August 2022. Retrieved 3 August 2022.
  59. "Vogtle Unit 3 starts nuclear fuel load". www.georgiapower.com. Archived from the original on 2022-10-15. Retrieved 2022-10-17.
  60. "NRC: Backgrounder on Emergency Preparedness at Nuclear Power Plants". www.nrc.gov.
  61. Bill Dedman, Nuclear neighbors: Population rises near US reactors, NBC News, April 14, 2011 http://www.nbcnews.com/id/42555888/ns/us_news-life/t/nuclear-neighbors-population-rises-near-us-reactors/#.XPHsAehJEgw Accessed May 31, 2019.
  62. Bill Dedman, "What are the odds? US nuke plants ranked by quake risk," NBC News, March 17, 2011 http://www.nbcnews.com/id/42103936 Accessed April 19, 2011.
  63. http://msnbcmedia.msn.com/i/msnbc/Sections/NEWS/quake%20nrc%20risk%20estimates.pdf [bare URL PDF]



На других языках


[de] Kernkraftwerk Vogtle

Das Kernkraftwerk Vogtle liegt in der Nähe von Waynesboro, Burke County im Osten des Bundesstaates Georgia. Der Fluss bildet dort die Grenze zum östlich gelegenen South Carolina. Das Kernkraftwerk liegt etwa 40 Kilometer südlich von Augusta.[1][2][3] Am 12. März 2013 wurde der Bau zweier weiterer Kraftwerksblöcke begonnen.[4][5] Der letzte Neubau in den USA war 1978 genehmigt worden.[6][7]
- [en] Vogtle Electric Generating Plant

[ru] АЭС Вогтль

АЭС Вогтль (произносится [воугл]) (англ. Vogtle Electric Generating Plant) — действующая атомная электростанция на юго-востоке США.



Текст в блоке "Читать" взят с сайта "Википедия" и доступен по лицензии Creative Commons Attribution-ShareAlike; в отдельных случаях могут действовать дополнительные условия.

Другой контент может иметь иную лицензию. Перед использованием материалов сайта WikiSort.org внимательно изучите правила лицензирования конкретных элементов наполнения сайта.

2019-2024
WikiSort.org - проект по пересортировке и дополнению контента Википедии