Coryton Power Station is a 732 MW Combined Cycle Gas Turbine (CCGT) gas-fired power station at Coryton, Thurrock, Essex, UK.
Coryton Power Station | |
---|---|
![]() | |
![]() | |
Country | England, United Kingdom |
Location | East of England, Essex |
Coordinates | 51°30′43″N 0°30′29″E |
Status | Operational as per UK capacity market |
Construction began | 2000 |
Commission date | 2002 |
Construction cost | £470 million |
Owner(s) | Intergen |
Operator(s) | Coryton Energy Ltd |
Thermal power station | |
Primary fuel | Natural gas |
Turbine technology | Combine Cycle Gas Turbine |
Site area | 5.2 hectare |
Chimneys | 2 (55 metres) |
Cooling towers | Air Cooled Heat Exchanger |
Cooling source | Air Cooling |
Combined cycle? | Yes |
Power generation | |
Units operational | 2 |
Make and model | Alstom GT26 A/B |
Nameplate capacity | 732 MW |
External links | |
Commons | Related media on Commons |
The site was part of the Coryton Refinery before its closure in 2012. Owned by Intergen, Coryton Power Station was built by Bechtel between 2000 and 2002, and cost £470 million. It was commissioned in 2002 and is run by Coryton Energy Ltd.
It is a CCGT type power station that uses natural gas. Gas is supplied to the site through a 7 km underground pipeline from an off-take from the National Grid Gas National Transmission System south of Stanford-le-Hope. It has two ABB Alstom GT26 gas turbines driving two electricity generators. Gas turbine exhaust gas is led to two heat recovery steam generators. These power one steam turbine, connected to a further generator. The station connects to the electricity National Grid at the nearby 400 kV Coryton South substation.
Gateway Energy Centre is a proposed 1250 MW gas-turbine power station to be located on the London Gateway Logistics Park about 1 km west of Coryton power station. It will be either a gas-fired 2 × CCGT plant; a 1 × CCGT plus 1 × Open Cycle Gas Turbine (OCGT) facility, and/or a 320 MW battery energy storage system.[1] It will be developed by InterGen. Original consent was granted in 2011, with subsequent revisions and consents granted in 2014 and 2016. CO2 capture facilities will be installed if mandated.[1] Construction is likely to start in 2022 with commercial operation expected in 2024.[2]
In 2020 InterGen gained consent for a 640 MWh lithium-ion battery storage power station near the site, capable of delivering 320 MW for nearly 2 hours. The £200 million project is expected start in 2022 and become operational in 2024.[3]
Electricity generation in the East of England | |||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Companies |
| ![]() | |||||||||||||||||||||||||||||||||||||||||||
Power stations |
|