Berke Dam (Turkish: Berke Barajı) is concrete arch-gravity dam built on the Ceyhan river in southern Turkey. There is a hydroelectric power plant, established in 2001 at the dam, with a power output of 510 MW (three facilities at 170 MW each).[1][2] "Technical Data" Tunnels = Water Intake Tunnel: 7200 meter; Highway Access Tunnel: 4300 meter & Grouting galleries; HRT: 6200 meter

Berke Dam
LocationTurkey
Coordinates37.373256°N 36.461347°E / 37.373256; 36.461347
Construction began1995
Opening date1999
Dam and spillways
ImpoundsCeyhan River
Height201 m (659 ft)
Reservoir
Total capacity427,000,000 m3 (346,175 acre⋅ft)
Power Station
Turbines3 x 170 MW
Installed capacity510 MW
Annual generation1670 GWh

References


  1. Structurae - Berke Dam
  2. "Berke Barajı" (in Turkish). www.duzici.bel.tr. Archived from the original on 2015-07-09. Retrieved 2015-07-08.




На других языках


[de] Berke-Talsperre

Die Berke-Talsperre (türkisch Berke Barajı) ist eine Talsperre mit einer 201 Meter hohen Bogenstaumauer im Süden der Türkei in den Provinzen Osmaniye und Kahramanmaraş, die den Fluss Ceyhan zum Zweck der Energiegewinnung aufstaut. Das Wasserkraftwerk in einer Kaverne verfügt über drei 172 MW-Francis-Turbinen.[1] Das Regelarbeitsvermögen beträgt 1672 GWh im Jahr.
- [en] Berke Dam



Текст в блоке "Читать" взят с сайта "Википедия" и доступен по лицензии Creative Commons Attribution-ShareAlike; в отдельных случаях могут действовать дополнительные условия.

Другой контент может иметь иную лицензию. Перед использованием материалов сайта WikiSort.org внимательно изучите правила лицензирования конкретных элементов наполнения сайта.

2019-2024
WikiSort.org - проект по пересортировке и дополнению контента Википедии