energy.wikisort.org - Power_plant

Search / Calendar

The Belwind Wind Farm is located on Bligh Bank, 46 kilometres (29 mi) from the Belgian port of Zeebrugge, and has been built in two phases. It has a 330 MW production capacity and an estimated annual output of 1.1 TWh.[1] Phase 1 had a 165 MW production capacity.[2]

Belwind
CountryBelgium
LocationOstend, Zeebrugge region, North Sea
Coordinates51°39′36″N 2°48′0″E
StatusOperational
Commission date9 December 2010 (2010-12-09)
Owner(s)Belwind NV
Wind farm
Type
  • Offshore
Distance from shore46 km (29 mi)
Hub height72 m (236 ft)
Rotor diameter90 m (295 ft)
Site area13 km2 (5 sq mi) (phase 1)
22 km2 (8 sq mi) (phase 2)
Power generation
Units operational55 x 3 MW (phase 1)
50 x 3,3 MW (phase 2)
Make and modelVestas V90-3MW
Vestas V122-3,3MW
Nameplate capacity330 MW
External links
Websitebelwind.eu/en/home
CommonsRelated media on Commons

Financing


Bligh Bank is the first stage of what is planned to be a 330 MW project. It was financed under a Project Finance structure by Project Company ‘Belwind’, after a number of delays[3] that included bankruptcy of developer Econcern.[4] Financial close was eventually reached on July 27, 2009. Bligh Bank is only the third offshore wind farm to be Project Financed, following Q7 and Thornton Bank. The €614 million deal sees Colruyt Group, the Colruyt family, SHV, ParticipatieMaatschappij Vlaanderen, Meewind and Rabo Project Equity, come together to invest in the construction of the 165 MW first stage of the Project.[5] For the first time the European Investment Bank will assume project finance risk for an offshore wind farm, by granting €300 million towards financing the Project.[6][7]

In January 2011 SHV sold its 20,7 % equity-share to the other Belgian shareholders Colruyt Group, the Colruyt family and ParticipatieMaatschappij Vlaanderen.[8] The financial close of the Second Phase of the project was on 6 October 2015.


First phase


Construction of the first phase commenced in August 2009 and was completed on 9 December 2010.[9][10] The wind farm includes an Offshore High Voltage Station which converts the infield 33kV to the export cable (150kV). This export cable is connected to the second high-voltage station, (the Booster Transformer Station) in Zeebrugge.[11][12] In 2012 Alstom planned to install a wind turbine of 6 MW Haliade as a test,[8][13] which happened in November 2013.[14][15][16]


Second phase


The construction of the second phase was mostly in 2016, with the first foundation on 12 May, first turbine on 27 of October and first electricity production 9 January 2017. The park has been fully commissioned as of 24 May 2017.


Revenue


The Belwind Wind Farm has a green certificate, meaning it will receive a set minimum price through Elia, €107 per MWh for the first 216 MW, the remaining 114 MW will receive €90 per MWh.[17] In 2011 it received €49,51 per MWh through the sale of the generated electricity to Electrabel.[8][18]


See also



References


  1. "Zeewind 1".
  2. Van Oord has completed Belwind Archived July 17, 2011, at the Wayback Machine Van Oord, 9 December 2010. Accessed: 10 December 2010.
  3. "Background to Belwind Financing". Retrieved 2009-08-03.
  4. "Econcern file for bankruptcy". Reuters. 2009-05-26. Retrieved 2009-08-03.
  5. "Belwind Press Release" (PDF). Archived from the original (PDF) on 2016-01-18. Retrieved 2012-12-20.
  6. "EIB Press Release". Archived from the original on 2009-09-10. Retrieved 2009-08-04.
  7. "EIB Financing details" (PDF). Retrieved 2012-12-20.
  8. "Meewind Participants meeting May 2012" (PDF). Retrieved 2012-12-20.
  9. Toespraak van Eerste Minister Yves Leterme bij de inhuldiging van het Belwind windturbinepark op de Blighbank (Noordzee) Archived 2011-07-06 at the Wayback Machine, 9 December 2010. Accessed: 10 December 2010.
  10. "Belwind - Nieuws". Archived from the original on 2011-07-20. Retrieved 2010-12-10.
  11. "Van Oord - EPC Contractor". Archived from the original on 2012-10-21. Retrieved 2012-12-20.
  12. "Belwind – 4C Offshore". Retrieved 28 March 2016.
  13. "Alstom 6 MW Haliade 150". Retrieved 2012-12-20.
  14. "First offshore installation of Alstom's Haliade 150", www.modernpowersystems.com, 22 November 2013
  15. De MonicaultMis, Frédéric (21 November 2013), "Alstom installe sa première éolienne en mer", www.lefigaro.fr (in French)
  16. "Belwind Alstom Haliade Demonstration - 4C Offshore". Retrieved 28 March 2016.
  17. "Minimum price and legal fram". Retrieved 2012-12-20.
  18. "Meewind participating in Belwind" (PDF). Retrieved 2012-12-20.





Текст в блоке "Читать" взят с сайта "Википедия" и доступен по лицензии Creative Commons Attribution-ShareAlike; в отдельных случаях могут действовать дополнительные условия.

Другой контент может иметь иную лицензию. Перед использованием материалов сайта WikiSort.org внимательно изучите правила лицензирования конкретных элементов наполнения сайта.

2019-2024
WikiSort.org - проект по пересортировке и дополнению контента Википедии