energy.wikisort.org - Power_plant

Search / Calendar

The Misicuni Multiplepurpose Project, better known as the Misicuni Dam, is a concrete-face rock-fill dam constructed on the Misicuni River about 35 km (22 mi) northwest of the city of Cochabamba, Bolivia. The dam will divert water from the Misicuni River to the Cochabamba Valley for several purposes to include providing water for irrigation and municipal water uses. In addition, the dam has an associated 120 MW hydroelectric power station, powered by 3 turbines 40 MW each.[5] Construction on the dam began in June 2009 but was halted in November 2013 due to contract disputes. The company finished the construction and is started the operations in September 2017.[6][7]

Misicuni Dam
Location of Misicuni Dam in Bolivia
CountryBolivia
LocationCochabamba Department, Cochabamba
Coordinates17°5′48.66″S 66°19′48.53″W
PurposePower, irrigation, municipal water
StatusOperational
Construction beganJune 2009
Opening date2017
Owner(s)Empresa Misicuni
Dam and spillways
Type of damEmbankment, concrete-face rock-fill
ImpoundsMisicuni River
Height120 m (390 ft)
Length434 m (1,424 ft)
Elevation at crest3,784 m (12,415 ft)[1]
Reservoir
Total capacity185,500,000 m3 (150,400 acre⋅ft)
Active capacity31,500,000 m3 (25,500 acre⋅ft)
Inactive capacity154,000,000 m3 (125,000 acre⋅ft)[2]
Surface area4.6 km2 (1.8 sq mi)
Normal elevation3,774 m (12,382 ft)
Misicuni Hydroelectric Plant[3]
Coordinates17°18′54.54″S 66°15′36.55″W
Commission date2017
TypeConventional, diversion
Turbines3 x 40 MW Pelton-type[4]
Installed capacity120 MW
Website
http://www.misicuni.gob.bo/ (Spanish)

Characteristics and costs


The project has three components:

The dam will be the highest and largest dam in Bolivia.[11] Misicuni project director Ramiro Saniz said in 2009 that the water from the Misicuni river is not sufficient to fill the reservoir and that other sources are needed.[10]


Background and construction progress


The public company in charge of developing the project is Proyecto Misicuni, an entity created by law in 1987. The contractor for the US$90 million dam component is the Consorcio Hidroelectrico Misicuni (CHM). The Misicuni consortium, led with 51 percent ownership by Grandi Lavori Fincosit S.p.A. of Italy, was the sole bidder for the project. Bidding was limited to Italian companies and CHM was the only company to submit a bid.[8][10] The consortium also includes Bolivian, Colombian and Venezuelan firms.[12]

The dam component was originally expected to be completed in 2014. However, in November 2013 the contract was canceled amid delays because CHM "failed to pay for pension funds, health insurances and other labour benefits and to contract key technical personnel."[13]


Benefits


The tunnel provides 4.5-7.5 million cubic meters of water per year to Cochabamba since 2005,[14] depending on whether the flow of the river is low or high and supplying about 10 percent of the city's drinking water. Once the dam will be completed, the amount of drinking water available will increase tenfold to 63 million cubic meters per year.


Environmental and social impact


1365 people live in the reservoir area that will be flooded and will be relocated. The Tunari National Park will also be affected.[9]


Financing


The dam is partially financed by the Italian government through a 25 million Euro loan and the Development Bank of Latin America (CAF).[15] Total funding from Italy for Phased II and III is USD 93 million. Bolivia will have to pay back the loan over in 20 years with a 0.10% interest rate.[12]

The construction of the penstock, hydropower plant and power transmission line is funded by a US$101 million loan from the Inter-American Development Bank approved in 2009.[16] These works were expected to be completed by 2015, but were only 30 percent completed as of April 2013.[17]


References


  1. Erik Muñoz Vargasm; Juan Pablo Rojas A.; René C. Murillo; Jaime Ponce B. (October 2010). "Multiple Project Misicuni" (PDF). Journal Boliviano de Ciencias (in Spanish). 7 (21). ISSN 2075-8936. Retrieved 7 January 2015.
  2. "Estudio de Evaluación de Impacto Ambiental Proyecto Misicuni Fase I" (in Spanish). Empresa Misicuni. September 2007. Retrieved 7 January 2015.
  3. "Misicuni: Proyecto Hidroelectrtico de Energia Renovable" (in Spanish). Banco Interamericano de Desarrollo. p. Annex Page 2. Retrieved 6 January 2015.
  4. "Misicuni Renewable Energy Hydroelectric Project". Inter-American Development Bank. Retrieved 6 January 2015.
  5. "Misicuni embalsa 55 por ciento de su capacidad y alistan tercera fase". Los Tiempos. 17 February 2019.{{cite web}}: CS1 maint: url-status (link)
  6. "CFRD project update".
  7. "Bolivia seeks bids to complete interrupted dam work on 80-MW Misicuni hydro project". Hydro World. 23 May 2014. Retrieved 6 January 2015.
  8. "Bolivia signs Italian firm to build Misicuni Dam". HydroWorld. 28 May 2009. Retrieved 9 December 2013.
  9. "Misicuni Dam Profile". dams-info.org. Retrieved 9 December 2013.
  10. "Bolivia, Cochabamba: work on Misicuni dam and water supply services set to start". 28 January 2009. Archived from the original on 18 December 2013. Retrieved 9 December 2013.
  11. Fernández, Jorge (2012-04-03). "Represa de Misicuni llega a 24 metros de altura y avance de 25 por ciento". Opinión. Cochabamba. Retrieved 2012-07-26.
  12. "Bolivia: Italian government to provide US$93mn for Misicuni project". 6 October 2009. Retrieved 9 December 2013.
  13. "Bolivia's Empresa Misicuni cancels contract for dam construction". SeeNews. Renewables. Retrieved 8 December 2013.
  14. "Proyecto Misicuni: Volumines entregados a SEMAPA 2005-2013". Empresa Misicuni. Archived from the original on 11 December 2013. Retrieved 8 December 2013.
  15. Vásquez, Katiuska (2012-07-23). "Gobernador no descarta que Misicuni pierda crédito italiano". Los Tiempos. Archived from the original on 2012-07-26. Retrieved 2012-07-26.
  16. "BO-L1043 : Misicuni Renewable Energy Hydroelectric Project". IDB. Retrieved 8 December 2013.
  17. "IDB BO-L1043 - Misicuni Renewable Energy Hydroelectric Project: Progress Monitoring Report May 2013". Inter-American Development Bank. Retrieved 8 December 2013.
Map all coordinates using: OpenStreetMap 
Download coordinates as: KML

На других языках


[de] Talsperre Misicuni

Die Talsperre Misicuni (spanisch Proyecto Múltiple Misicuni oder Presa Misicuni) ist eine Talsperre mit Wasserkraftwerk im Departamento Cochabamba, Bolivien. Sie staut den Río Misicuni zu einem Stausee auf. Die Talsperre befindet sich ca. 35 km nördlich der Stadt Cochabamba.
- [en] Misicuni Dam



Текст в блоке "Читать" взят с сайта "Википедия" и доступен по лицензии Creative Commons Attribution-ShareAlike; в отдельных случаях могут действовать дополнительные условия.

Другой контент может иметь иную лицензию. Перед использованием материалов сайта WikiSort.org внимательно изучите правила лицензирования конкретных элементов наполнения сайта.

2019-2025
WikiSort.org - проект по пересортировке и дополнению контента Википедии